Industrial silo

Selective demolition of a tall structure with recovery of materials.

Key figures
20 mHeight
2 silosUnits
10 daysDuration
95%Recycling

From start to finish. No surprises.

Every project follows a documented, step-by-step process. These are real photos of this dismantling job.

01
BeforeStarting point
Two industrial silos before dismantling
Before

Two industrial silos before dismantling

02
DuringWork in progress
Selective demolition with high-reach machinery
During

Selective demolition with high-reach machinery

03
AfterEnd result
Cleared ground and sorted materials after the silos were demolished
After

Cleared ground and sorted materials after the silos were demolished

Selective demolition of two industrial silos used to store food raw materials. Work at height, with all materials segregated at source to maximise the recycling rate. Operational installations close by meant dust and vibration had to be tightly controlled.

Top-down demolition with high-reach machinery. Dust control by continuous water spraying. Segregation at source of steel, concrete and other materials. Transport to the recycling plant with our own fleet.

Project challenges

1A tall structure that required specialist work at height
2Segregation of materials at source
3Close to other operational installations
4Managing dust and particles during demolition